Huge white domes used to store wood pellets at Drax Power Station, linked by conveyor walkways, next to the concrete base of a cooling tower
File photo: Isaac Bee / Wikimedia Commons, CC BY 4.0 · Wood pellet storage domes at Drax Power Station, North Yorkshire, July 2024
Tech & OnlineUp to £20bn plan · first phase targets 2028 · no planning permission yet

Drax wants a giant AI data centre at Britain's most polluting power station

Why it hits youEvery time you use an AI app, the work happens in a data centre somewhere, and the UK wants more of them here. But they need enormous amounts of power, and the grid is so jammed that some projects can't connect until 2030. Drax has spare power on site. The row is about whether wood counts as clean: burning it releases CO2, but under international carbon accounting rules those emissions aren't counted as the power station's, on the basis that growing trees soak the carbon back up. That's why Drax is classed as renewable and gets subsidies paid for through energy bills.

Drax runs a huge power station near Selby in North Yorkshire that burns wood pellets instead of coal. Today it signed a deal with the investment giant Brookfield and its AI company Radiant to build a data centre on the site, with total spending that Brookfield says could top £20bn. A data centre is a giant warehouse full of computers. AI tools like chatbots run on thousands of powerful chips that need electricity day and night, plus cooling to stop them overheating. Drax and ministers say the plan means jobs and growth in the North. Climate campaigners say it would keep the UK's biggest single source of CO2 burning wood for longer.

The Facts

What everyone agrees on

Before anyone spins it. Every one of these is checkable.

  • Drax has signed a deal with Brookfield and its UK-based AI company Radiant to develop a data centre at Drax Power Station. Brookfield estimates total investment, including computer chips, could exceed £20bn, starting with £2.5bn for the first phase. Drax ↗

  • Phase one is a data centre of up to 100MW, powered from the national grid, aiming to open in early 2028. Phase two aims for 500MW between 2028 and 2031, powered directly by the power station, with more capacity after 2031. Drax (stock market announcement) ↗

  • The first phase still needs planning permission, regulatory and grid approvals and a customer to use it, and no final decision to invest has been made. CNBC ↗

  • Drax produces almost 5% of the UK's electricity by burning wood pellets, which makes it the UK's single largest emitter of carbon dioxide, according to analysts. The Guardian ↗

  • Drax received a record £999m in subsidies in 2025, around £13 per household, because emissions from burning wood are zero-rated in carbon accounting. Payments are due to halve to about £460m a year from 2027. Ember ↗

  • Drax's new subsidy contract, from April 2027 to March 2031, covers about 30% of the station's output. It lets Drax ask to use up to 500MW to power a data centre, but the government must agree, weighing value for money, energy security and sustainability. Drax (stock market announcement) ↗

  • In last week's Budget, the Chancellor launched a Data Centre Covenant, promising key data centres grid connections and, where necessary, permission to build their own power generation while they wait. GOV.UK (Budget speech) ↗

  • Drax shares rose 8.5% to 877p after the announcement. Last month Microsoft pulled out of an Nscale data centre in Essex that couldn't get a grid connection until at least 2030. City AM ↗

Every Side · 1 of 3

Drax, its partners and the government

Spare power, ready-made grid links and jobs in the North

Drax boss Will Gardiner says the project can “help secure the long-term future of the site and protect hundreds of jobs”. He argues Drax is “one of the few UK sites that can provide large-scale reliable power directly to data centre customers by utilising existing and underutilised generation capacity”. Radiant's chief executive Mahdi Yahya says it would “give British researchers, startups and enterprises access to frontier compute at home”, meaning Britain wouldn't have to rely on computers abroad. Treasury minister Emma Reynolds says investments like this mean “creating good jobs in Yorkshire and delivering growth right across the country”. At last week's Budget, Chancellor John Healey promised that “critical data centres will get the grid connections they need, and, where necessary, be allowed to build onsite generation while they wait”.

Who's saying it
  • Will Gardiner, Drax chief executive
  • Mahdi Yahya, Radiant chief executive
  • Emma Reynolds, Chief Secretary to the Treasury
  • John Healey, Chancellor

Side labels are our editorial calls for now. How we'll rate lean

Every Side · 2 of 3

Climate campaigners

Burning trees to run computers isn't green

Campaigners have fought Drax's data centre idea all year. In May, Dr Mary Stevens of Friends of the Earth accused Drax of “attempting to use the boom in AI infrastructure to extend a lifeline to its dirty business”, adding: “Whatever it might say, Drax is not renewable energy.” Matt Williams of the US group NRDC said: “A data centre powered by Drax would burn millions of tonnes of trees every year.” Almuth Ernsting of Biofuelwatch warned that partners would be “signing up for expensive electricity from burning trees”. The think tank Ember says Drax got a record £999m in subsidies in 2025. Its analyst Frankie Mayo said: “British taxpayers should never have been in this position in the first place.” These comments came before today's deal was announced.

Who's saying it
  • Dr Mary Stevens, Friends of the Earth
  • Matt Williams, NRDC
  • Almuth Ernsting, Biofuelwatch
  • Frankie Mayo, Ember

Side labels are our editorial calls for now. How we'll rate lean

Every Side · 3 of 3

What it means for you

Your bills, local jobs and the AI you use

Bills: Drax's subsidies are paid through energy bills. Ember says they cost every UK household £13 in 2025, and they're due to roughly halve from 2027. The government's new Data Centre Covenant says data centres should cover “any energy costs they create - so households, communities and other businesses do not pick up the bill”. Jobs: Drax says the project protects hundreds of jobs at the power station, but no number has been given for new ones. Your AI use: the government wants about 6GW of AI data centre capacity in the UK by 2030 so that services like the NHS don't rely on computers overseas. Nothing is approved yet. Drax says a consultation with people living near the site will begin shortly, before any formal planning application.

Who's saying it
  • GOV.UK, Data Centre Covenant
  • Ember
  • Drax

Side labels are our editorial calls for now. How we'll rate lean

The Blindspot · what the headlines skip

Drax's fans skip how much wood the bigger plan could burn

The first phase runs on grid power, but later phases would be powered by the station itself. The US group NRDC estimated that powering about 1.1GW directly could need around 4.9 million tonnes of wood and produce 8.6 million tonnes of CO2 a year. Drax disputes those figures and hasn't committed to running the whole site on wood.

Data Centre Review ↗

The Blindspot · what the headlines skip

Campaigners skip that phase one doesn't burn extra wood, and Drax can't just switch

The first 100MW would draw from the national grid. Any direct supply from the power station before 2031 needs government approval, capped at 500MW. And when the regulator Ofgem made Drax pay £25m in 2024 over poor data on the Canadian wood it used, it found no evidence Drax had been wrongly given subsidies.

Drax (stock market announcement) ↗Ofgem ↗

The Blindspot · what the headlines skip

The £20bn is a hope, not a cheque

The £20bn is Brookfield's estimate if every phase gets built, and it includes computer chips. Only the first phase has a target date, and it still needs a customer and planning permission.

Drax ↗CNBC ↗

Your Call

Should a wood-burning power station be allowed to power Britain's AI boom?

Which side surprised you most?

Sides you've read
  1. Drax, its partners and the government: not yet
  2. Climate campaigners: not yet
  3. What it means for you: not yet

Only you can see this. It's saved on this device and never sent anywhere.

Receipts

Every source, one tap away

Don't take our word for it. This is everything the breakdown is built on.

Hero image: File photo: Isaac Bee / Wikimedia Commons, CC BY 4.0 · Wood pellet storage domes at Drax Power Station, North Yorkshire, July 2024 ↗

By No Glaze News · published

Next story John Lewis's Christmas ad is here: a glam granny, a talking dog and Sam Fender
Next story